Week 7 Renovation Status




Well things continue to go well in spite of the heat and humidity.  The roofer worked Friday, Saturday, and Sunday and may have a bit of work to finish up on Monday.  The electrician will be at the house on Tuesday and Thursday, hopefully, and Steve, Ken, and Dan will frame in the upstairs on Tuesday and Wednesday.  Terri and I removed the plaster and laths from two walls in the red room on the first floor (see before and after pictures above), and I cleaned and straightened up on the first floor.  The pantry by the back door is going to be great (see picture)!  What a great idea Jenny.  Moving the opening between the kitchen and the living room, taking out the stack, straightening the stairs, and putting in a pantry/closet are great ideas and will make the kitchen more functional.  I can't wait to get back in and reorganize. 